Region |
Steelmaker |
Time |
Equipment |
Affected Products |
Affected Quantity (10,000 tons) |
Note |
North China |
Jinxi Steel |
1 Dec. – 1 Jun. |
One bars production line |
Rebar |
0.3/day |
Resume production |
1 June (12 days and 18 days) |
Large size H-beam production line and medium size H-beam
production line |
H-beam |
15 |
|
North China |
Puyang Steel |
17 December 2018 |
1*800m3 BF |
Hot metal |
0.3/day |
|
North China |
Tangshan Ruifeng |
6 May |
1*450m3 BF |
Hot metal |
0.15/day |
|
7 May |
1*680m3 BF |
Hot metal |
0.23/day |
|
North China |
Tangshan Chunxing |
6 May |
1*1080m3 BF |
Hot metal |
0.32/day |
|
North China |
Tangshan Donghua |
6 May |
2*680m3 BFs |
Hot metal |
0.48/day |
|
North China |
Tangshan Kaiheng |
6 May |
1*1080m3 BF |
Hot metal |
0.32/day |
|
North China |
Tangshan Guoyi |
3 May |
1*680m3 BF |
Hot metal |
0.21/day |
|
North China |
Tangshan Guoyi |
3 May |
1*1080m3 BF |
Hot metal |
0.3/day |
|
North China |
Tangshan Delong |
19 May |
1*1080m3 BF |
Hot metal |
0.3/day |
|
North China |
Jinding Steel |
5 March (4 days) |
1*1080m3 BF |
Hot metal |
0.86/day |
|
North China |
Shougang Jingtang |
23 April (2 months) |
5500m3 BF |
Hot metal |
1.1/day |
|
North China |
Xintai Steel |
1-16 June 2019 |
H-beam production line |
H-beam |
0.35/day |
|
North China |
Tiantie |
Early June |
1750mm HR coil/plate production line |
HR coil/plate |
0.6/day |
|
North China |
Shougang Qianan |
25 June (40 days) |
1*2650m3 BF |
Hot metal |
0.65/day |
|
North China |
Shougang Qianan |
25 June (12 days) |
1*2250mm hot rolling production line |
HR coil/plate |
0.9/day |
|
North China |
Cangzhou CREC |
11 June (14 days) |
1*180t converter
1780mm HRC production line |
HR coil/plate |
11 |
|
Northeast China |
Beitai Steel |
1 June |
One wire rod production line |
Wire rod |
5 |
|
6 May |
1# 2850m3 BF |
Hot metal |
0.6-0.7/day |
|
Northeast China |
Jilin Steel |
Early December 2018 |
4*70t electrical furnaces |
Rebar and coiled rebar |
0.2/day |
|
Northeast China |
Benxi Steel |
26 April-11 June |
Steel bar production line |
Quality steel |
7.5-8 |
|
Northeast China |
Benxi Steel |
Early June (20 days) |
Galvanizing production line |
Galvanized sheet |
3 |
|
Northeast China |
Anshan Baode |
Early June (20 Days) |
Section steel production line |
Section steel |
10 |
|
East China |
Zenith Steel |
20 March(85
days) |
1*1580m3 BF |
Hot metal |
34 |
|
East China |
Zenith Steel |
9 April (15 days) |
Two rebar production lines |
rebar |
10 |
|
East China |
Zenith Steel |
12 May (20 days) |
One small size |
Quality & Special Steel |
3 |
Resume production |
East China |
Eastern Special Steel |
17 May (15 days) |
Small bar production line |
20-50mm small bar |
2-2.5 |
Resume
production |
East China |
Ningbo Steel |
12-27 June 2019 |
1780mm HR production line |
HRC |
19.5 |
|
East China |
Wuhu Xinxing Ductile Pipes |
10-15 June 2019 |
Quality wire production line |
Quality wire |
1.2 |
|
East China |
Changjiang Steel |
Mid-June (10 days) |
Rolled steel |
Bar steel |
2.5 |
|
East China |
Fangda Special Steel |
30 May -19 June 2019 |
2# 1050m3 BF |
Hot metal |
0.35/day |
|
East China |
Ansteel CR Plate (Putian) |
15 April |
Rolling, continuous annealing and galvanizing production line |
Rolled plate, common CRC and galvanized sheet |
2.6; 1.98; 0.6; |
|
East China |
Huanghe Special Steel |
1-16 June |
One section steel production line |
Section steel |
1.05 |
|
East China |
Weifang Special Steel |
16 May 2019 (15 Days) |
One quality wire production line |
5.5-20mm wire rod |
2.5 |
Resume production |
East China |
Weifang Special Steel |
20 June (20 days) |
Quality bar production line |
Round steel |
7 |
|
East China |
Sanming Steel Minguang |
27 May ( 22 days) |
1*420m3 BF |
Hot metal |
0.13/day |
|
East China |
Fujian Sanming Steel |
3-7 June |
One bar production line |
Bar steel |
1 |
|
East China |
Shandong chuanyang Steel |
1 June (15 days) |
Section steel production line |
4#-8# angle steel |
0.45/day |
|
East China |
Changzhou Eastern Special Steel |
Middle May |
Two steel bar production lines |
Steel bar |
3-4 |
|
Central South China |
Wuyang Steel |
16 May (15 days) |
4200mm medium plate mill |
Medium plate |
0.4/day |
|
Central South China |
Lianyuan Steel |
Early and middle June (10 days) |
cold rolling production line |
CRC |
5 |
|
Central South China |
Lianyuan Steel |
Early and middle June (5 days) |
1*120t converter |
rebar |
5 |
|
Central South China |
Shaoguan Steel |
26 May (6 days) |
No. 2 bar production line |
rebar |
0.2/day |
Resume production line |
Central South China |
Anyang Steel |
9 June |
Cold rolling annealing unit |
CRC |
0.2-0.25/day |
|
Central South China |
Anyang Steel |
31 May (15 Days) |
One cold rolling pickling production line |
Pickling product |
0.4/day |
|
Central South China |
Liuzhou Steel |
1 June |
High speed wire rod production line |
High speed wire rod |
0.3/day |
|
Southwest China |
Chongqing Steel |
1-16 June 2019 |
One bar production line |
Steel bar |
2.6 |
|
Southwest China |
Panzhihua Steel |
30 May-2 June 2019 |
One bar production line |
Steel bar |
0.15/day |
Resume production line |